Ranchi: An independent panel of experts appointed by the water resources department has warned that heavy vehicular movement on the Getalsud dam crest could cause cracks and rutting, weakening the structure.The department prohibited movement of all vehicles, including two-wheelers, three-wheelers, four-wheelers and heavy transport, on the crest from 9 am to 6 pm on Saturday to allow the panel to conduct a safety inspection.The restriction followed the panel’s initial visit on Friday, when excessive traffic obstructed inspections, measurements and observations of the crest, parapet wall, upstream and downstream slopes and appurtenant structures.During the evaluation, the experts said a dam crest was primarily intended to provide an alternative route for inspection, maintenance and emergency access, and not for regular public or heavy traffic. They termed continuous vehicular movement unsafe from a structural standpoint, saying dynamic loads and vibrations could cause surface cracking, rutting and damage to the guard wall.The panel warned that rainwater entering the dam body through cracks could compromise structural stability and damage instrumentation and survey pillars.Moti Lal Pingua, engineer-in-chief of the department, said the panel had flagged the risks associated with traffic on the structure. “They will be submitting a detailed report to us. Once we receive it, we will decide on the necessary measures to protect the dam, which may include restricting vehicular mobility on the crest,” he said.Following the panel’s recommendation, the department has decided to gradually enforce a complete ban on vehicular movement across the dam crest.Pingua said the panel was constituted under Section 38 of the Dam Safety Act, 2021, to conduct comprehensive dam safety evaluations across Jharkhand. The department will formulate an action plan for remedial works based on the panel’s final findings.Of the 63 dams in Jharkhand, 59 are under the water resources department, two under the drinking water and sanitation department and one under the energy department. Comprehensive safety evaluations have been completed for 20 dams, while assessments of the remaining structures are underway.The department is discussing World Bank funding for the repair and rejuvenation of the reservoirs. “We already meet several criteria to secure the funding, though a few formalities remain to be completed. We are hopeful of receiving the World Bank’s support,” Pingua said.